We have every reason to believe we can meet our first milestone of having the first third of the building under roof by the end of the year. The process involves:

  • Finishing the support columns in the basement
  • Pouring the slab on grade in the basement
  • Framing the eastern third of the building by floors 1-4
  • Setting the roof truss system
  • Placing the roof to "dry in" the areas beneath so that the following trades of mechanical, electric and pluming can start their work

This new Phase II project is going to change the way you think about active senior living, check back often for more updates!