This Phase II construction at The Garlands is going to set the standard for active retirement communities nationwide, and will shift perceptions of what independent senior living can be. As such it is a complex and sophisticated undertaking.

Since it's raining today, I thought I'd explain a little about our plan of attack. We are building the second phase of The Garlands in three vertical sections--starting with the east, moving to the center and finishing with the western portion of the building. We are building vertically vs. horizontally (meaning floor-by-floor) because we feel there are better economies of scale in doing so. In this manner we can have greater efficiencies with the tradespeople, meaning our lead trades can go in creating the "bones" of the first third of the building and then clear the first vertical, making way so the following tradesmen--mechanical, electric and plumbing--can start their work.