Phase II of The Garlands is making great strides; our latest progress being in Building D, the superstructure of which was completed on schedule in August 2009. And a model unit--showcasing the luxurious living offered by our new residences--is finished and ready for visitors. We hope you can stop by and take a look!

Other progress you'll notice on your visit:

Roof trusses for this project are quite complicated and have been described by many as a most challenging geometric design. But the challenge has been met and these trusses are nearly complete at the west end of the building with the final roofing scheduled for completion by Thanksgiving.

With the completion of the roof trusses, the huge crane seen looming over our site has recently been dismantled and removed as its work is done.

The installation of the trusses and roofing enables the work on the exterior walls to progress. The exterior masonry is now 85% complete with the anticipated completion of all exterior wall masonry is mid November.

The Garlands goes green:

Insulation board is being installed behind the masonry, and when combined with the fiberglass insulation within the walls, we'll get exceptional energy efficiency in the residential units. In addition, the exterior Tyvek wrap system has been designed and installed per DuPont's standards to include special fasteners and flashing around the windows, all done to provide excellent protection against water intrusion through the exterior wall. All told, these will be extremely well made and efficient residences, which are easy on the heating/ cooling bills, as well as friendly to mother nature.

The east half of the building is already weather-tight, allowing the interior to be finished. The mechanical, electrical, HVAC and plumbing tradesmen have already completed their rough-in work in the east half of the building. In this location, drywall is being installed as well as ceramic tile, wood doors, millwork, cabinets, painting and appliances.

The residential units at the east end of the building will start to approach completion by this year's end. This completion sequence will march west through the building throughout the winter months.

At ground level, the building will begin to take it's final form during late Summer of 2010 when driveways will be paved, landscaping installed and construction trailers removed.

The current schedule targets building completion by October 2010--less than one year away!